Integrated Delivery & Supplier Management

Connecting Suppliers into One Delivery Plan

Bringing multiple external suppliers and internal teams onto one integrated plan with clear handoffs.
1.Context
A technology programme involving multiple external suppliers and internal delivery teams.
2.The challenge
Each supplier worked to its own plan, making integrated progress difficult to assess and creating delays at handoff points.
3.My role
Delivery leadership responsible for integrated planning and supplier coordination.
4.Actions and approach
  • Created an integrated plan with agreed handoff points.
  • Introduced joint risk and dependency reviews.
  • Clarified contractual and practical responsibilities at interfaces.
5.Outcome
Created a coordinated delivery approach across internal teams and external suppliers, with clearer handoffs, shared dependency management and defined responsibilities at critical interfaces.
6.Lesson for prospective clients
Complex projects often fail between teams rather than within them. Interfaces need owners.